Transit Advisory Committee
Thu, September 14, 2023
Transit Advisory Committee — September 14, 2023
This was a regular meeting of the Petaluma Transit Advisory Committee, featuring a detailed presentation from SMART rail on the upcoming Petaluma North station and a substantive business item related to fleet electrification infrastructure.
General Public Comment
Dan Likeped, representing Petaluma Urban Chat, invited committee members and the public to the Better Cities Film Festival, screening September 20th at the Boulevard Cinemas and September 28th at Santa Rosa Junior College's Carol Ellis Auditorium. He noted that a short film on Zurich's transportation system would be of particular interest to this body, and that free tickets had been sent to committee members. Maria Arrey of Petaluma Transit staff was announced as an official welcomer at each screening.
SMART Presentation: Petaluma North Train Station
Emily Betts, Planning Manager for SMART, and Michael Wiltermood, Senior Engineer and project lead, presented an update on the Petaluma North Station and related infrastructure work.
Betts opened with a SMART system overview, noting that August 2023 ridership hit 72,000 — exceeding pre-pandemic levels — making SMART the top rail agency in California for ridership recovery. Recent initiatives under new General Manager Eddie Cummins include restored and expanded service, reduced fares, suspended parking fees, overnight parking at stations, free K–12 field trips, a Friday/Saturday late-night "Starlighter" service, and a summer free-youth-fare program in partnership with Petaluma Transit and other North Bay agencies. SMART also launched a microtransit shuttle at the Charles M. Schulz–Sonoma County Airport station that coordinates on-demand rides with train arrivals and departures.
Wiltermood then described the Petaluma North Station project. The station will be located at Corona Road near McDowell Boulevard on a former industrial site. Key details:
Public comment on the SMART presentation (belatedly opened after the committee chair realized the step had been skipped): One community member who identified herself as a regular user of the SMART path expressed strong enthusiasm for the project, noting connectivity improvements for seniors and cyclists at the McDowell crossing. She mentioned organizing a transit group at a local senior apartment complex and praised the bus-train-bike connectivity the station will provide. Vice Mayor Healy (sitting as a committee member) raised the potential for coordination with SRJC, Petaluma Health Center, and local microbreweries. Wiltermood confirmed that SMART plans to begin working with partner destinations about six months before the station opens. Committee member Fry, who lives in the Petaluma Estates neighborhood adjacent to the crossing, thanked SMART for improving safety and accessibility at the grade crossing, citing a recent bicycle fall caused by the skewed rail angle and noting the crossing is currently difficult for seniors using wheelchairs, walkers, or canes.
Committee Chair raised a pointed concern that calling the station "Petaluma North" does not reflect how locals orient themselves (east/west is more typical), and separately noted that the retail parcel appears to be a leftover, inconveniently located space rather than a well-integrated amenity — though he acknowledged it was too late in the process to change.
No formal vote was taken; this was an informational presentation.
Approval of Minutes — July 13, 2023
Minutes were approved without correction or discussion.
Vote: Approved by motion (mover not clearly identified in transcript), no dissent.
Resolution Authorizing Purchase of Electric Switchgear from Wesco Distribution
Transit Manager Jared Hall presented this item as a critical step in the electrification of the Petaluma Transit facility. The core issue: before the agency can receive and operate electric buses, it must upgrade the transit yard's electrical infrastructure. One key component — an electric switchgear unit (3,200-amp, 480-volt, three-phase) — has a current build/lead time of 60 to 70 weeks due to supply chain constraints. Other agencies have received electric buses they cannot use because this piece of hardware wasn't ordered in time.
Hall explained that the city is working with consultant NV5 on facility electrical design (currently at ~50% design) and that the switchgear is being purchased through a Sourcewell joint purchasing agreement. The estimated cost is approximately $140,000 plus a 10% contingency, for a total just under $155,000. Funding comes primarily from a $180,000 PG&E EV Fleet Program grant awarded to the city for electric infrastructure upgrades.
The switchgear will eventually support 10 chargers with two plugs each, capable of serving up to 20 vehicles simultaneously — covering 80–90% of the current fleet of approximately 25 vehicles (fixed route, paratransit, and support). Charging time is estimated at 6–8 hours overnight, which aligns with Petaluma Transit's existing downtime window (roughly 9 p.m. to 6 a.m.).
Committee members raised several questions: whether the equipment would be sufficient for full fleet electrification (answer: yes, for at least 80–90% of the fleet); whether buses might arrive before the switchgear (Hall said timelines are aligned but acknowledged risk of delays, noting that an expedited build would have cost ~50% more); and whether noise impacts on nearby housing had been studied (Hall said no formal study was required under CEQA exemption but flagged it for monitoring during design). Committee member Cinq also asked about backup charging options in case of grid disruption — Hall noted this is an ongoing discussion, with options including coordination with Sonoma County Transit, Santa Rosa CityBus, and Petaluma City Schools' electric school bus yard, though the scale of battery backup needed for a full EV fleet is significant.
The committee voted to recommend that the City Council adopt the resolution authorizing the purchase.
Vote: Moved by Aldén, seconded by Cinq. Approved unanimously (Abrams – yes, Aldén – yes, Kol-Ross – yes, Healy – yes, Cinq – yes, Post – yes).
Transit Manager Report
Manager Hall highlighted several items:
Key Takeaways
AI-generated summary from voice-to-text transcript. Not the official record. Verify important details with the source documents linked above.
What happened at this meeting
SMART – Presentation on Petaluma North SMART Train Station
Approval of Minutes for the July 13, 2023 Meeting
Discussion and Recommendation of a Resolution Authorizing the Purchase of Electric Switchgear from Wesco Distribution and Approving Staff to Execute All Related
Transit Manager Report
Agenda items (4)
What happened
SMART Planning Manager Emily Betts and SMART Senior Engineer Michael Wiltermood presented information on recent SMART initiatives and an update on the Petaluma North SMART Station. Public comment included Sheila Baker expressing support for the station and future electric transit, and Vice Mayor Janice Cader Thompson inquiring about Corona Rail Crossing safety and pedestrian/bike access improvements. Vice Chair Kaljian and Committee Member Abrams asked follow-up questions, with SMART Senior Engineer Wiltermood responding with details on planned updates.What happened
Minutes from the July 13, 2023 meeting were deemed approved.What happened
Staff Liaison Hall provided an overview of the proposed purchase of electric switchgear from Wesco Distribution. A motion to recommend the resolution was made by Council Member Pocekay and seconded by Vice Chair Kaljian, passing 6-0 with no opposition.What happened
Staff Liaison Hall provided updates on the Fare-Free Youth Program, discussed a Petaluma Transit meeting with Amtrak staff regarding a potential thruway bus addition to Petaluma Transit, announced upcoming Microtransit ad-hoc subcommittee discussion topics for the September 21, 2023 meeting, and mentioned planned film festival attendance.Additional votes recorded in minutes
Approve minutes for the July 13th meeting
Approve resolution authorizing purchase of electric switch gear